Friday, January 15, 2010

Zelda is Crowned

This has been a very busy week at Zelda with three (3) different contractors working at once.  As of Thursday, Zelda has been crowned in every room.  We have the new trim carpenter working downstairs, the Workmans upstairs and our electrican shows up every now and then.

The downstairs trim carpenter has trimmed out six (6) windows, two (2) doors, two (2) large openings in the foyer and began installing the front door.

The Workman have leveled out the floor on one (1) of the upstairs bedrooms and installed new hardwood, baseboard and crown molding and trimed out the two (2) windows.  They will continue to finish the original work upstairs and I am sure Brent has few other items planned in the coming weeks.

The electrican has completed the install of all the undercabinet lighting and only has a few punch list tiems remaining.

We had the secruity alarm company stop in at Zelda and hook up the alarm system now that we have power.  It works good and has a loud horn.

Lynn has started the grouting on the kitchen backsplash and Brent has started tiling the upstairs hall bathtub.  He installed slate tile in the keeping room hearth on Wednesday night.

Friday is our last full day before heading to Maryland on Saturday.

No comments:

Post a Comment