Monday, March 17, 2008

Electrical Sighting

The soffit and facial board installation is complete and Zelda has tranformed once again. The is the start of the trim out and it looks great. We meet in Kings Mountain this weekend, Brent coming in from Chattanooga and Lynn, Jennifer, Jessica and Cookie arrived from Holly Springs. It was a weekend full of nail pulling, installing door headers, finishing the upper levels of wall framing and bracing below all the second story windows.






There was actually a sighting of our electrical contractor who was at Zelda all day on Saturday. Nearly all the wiring as been pulled for the electrical boxes, just no home runs back to the panel. This "two" week job that was quoted which Brent budgeted for five (5) weeks may turn into a three (3) month job.
Once the electrical is installed and inspected Brent will have the alarm company install all their wiring, and then the sheet rock can be installed. Then finally and I mean finally, those kitchen cabinets purchased in August of 2007 can be installed.